Navigating Project Evolution

A Comprehensive Impact Analysis of Change Requests in Project Management Simulation

Presentation image

Slide 1: Change is Inevitable

Understanding the Ripple Effect of Change Requests

Image URL: https://cdn.prod.website-files.com/652427f5a7e6506...
  • Assessment 2 Overview: This is the Project Management Simulation Impact Analysis of Change Requests for Assessment 2. It is based on data from Assessment 1.
  • Project Lifecycle: We will delve into the project's current state to show how the old factory has been converted to a sustainable data centre.
  • Budget Considerations: The original budget was £100M for the project. Key risks and stakeholders were identified in the Assessment 1 as well.
  • Original End Date: Originally, the project was expected to end on Day 211. This target completion date would make the inaugural festival.
Change is Inevitable image

Slide 2: Roadmap to Adaptation

A Structured Approach to Handling Project Modifications

Image URL: https://www.smartsheet.com/sites/default/files/202...
  • Plan in Baseline Project: We begin with the baseline project plan as our starting point, which has WBS, Gantt, Cost Baseline, Risk and Communication Plans.
  • Analyzing Change: We will thoroughly analyze Change Requests 1–4, evaluating their impact on the project's scope and objectives.
  • Integrating Updates: This step involves integrating the approved changes into the project plan, updating relevant documents, and revising the schedule.
  • Forward Vision: Discussing the next steps to finalize the project and listing references for this presentation and for the audience.
Roadmap to Adaptation image

Slide 3: Project Foundation

Revisiting the Initial Plans and Objectives

Image URL: https://images.examples.com/wp-content/uploads/201...
  • WBS & Gantt Chart: The project's Work Breakdown Structure (WBS) and Gantt chart serve as visual representations of tasks and timelines.
  • Cost Baseline: The Cost Baseline provides a benchmark for measuring project expenditures and managing budget adherence for various tasks.
  • Risk & Communication: The Risk Plan outlines potential risks and mitigation strategies, while the Communication Plan ensures transparent stakeholder updates.
  • Objective Overview: The primary objective is converting an old factory into a sustainable data center. Original end Day 211 (Inaugural Festival).
Project Foundation image

Slide 4: Special Thank-You Event

Adding a VIP Event to the Project Timeline

Image URL: https://www.smartsheet.com/sites/default/files/IC-...
  • New Task Implementation: Adding Summary Task 5 with activities 21–28 (VIPs, venue, catering, logistics, rehearsal, execution, closeout).
  • Schedule Extension: This extends the schedule to Day 250 on the critical path (Slack = 0). This is a significant shift due to the added event.
  • Budget Allocation: Allocate £150k for event (venue, AV, catering). This requires budget adjustments and careful allocation of resources.
  • New Risks: New risks include VIP no-show and vendor cancellation. Mitigate these with RSVPs and backup contracts with vendors.
Special Thank-You Event image

Slide 5: Budget Realignment

Adapting to Financial Adjustments

Image URL: https://images.squarespace-cdn.com/content/v1/5dea...
  • Festival Budget Cut: Festival budget is cut from £10M to £8.5M, necessitating strategic financial adjustments across project components.
  • De-scoping Deliverables: De-scope lower-priority deliverables and re-baseline cost line items. Shift £1.5M from 'Launch Event' to reserves.
  • Reallocation Strategies: Reallocating funds to essential project elements ensures core objectives are met despite budget constraints.
  • Quality Compromise: Address new risk of quality compromise through vendor negotiation, quality reviews to ensure project standards are upheld.
Budget Realignment image

Slide 6: Weather the Storm

Contingency Planning for Launch Day Weather

Image URL: https://amzirlodp-prd-s3.s3.amazonaws.com/document...
  • Rain Probability: There is a 90% rain probability on launch day, requiring preemptive measures to mitigate weather-related disruptions for the project.
  • Infrastructure Investment: Allocating £100k for a weather package, including tents, indoor backup locations, and incorporating a rain-date task in the WBS.
  • Schedule Slack: Insert 1-2 day slack to accommodate potential delays. This adds flexibility to the project schedule due to weather disturbances.
  • Mitigation Strategies: Mitigate adverse weather risks with covered venues and insurance. This minimizes the impact of weather-related issues.
Weather the Storm image

Slide 7: Cybersecurity Resilience

Addressing Security Vulnerabilities

Image URL: https://cybersolarium.org/wp-content/uploads/2024/...
  • Security Provider Breach: A security provider breach necessitates new security tasks to safeguard the project's sensitive data and operational integrity.
  • Proactive Measures: Add breach assessment, patching, audit, fallback manual security measures to address potential vulnerabilities due to security breach.
  • Emergency Cybersecurity Budget: Allocate £200k emergency cybersecurity budget to promptly address security incidents and fortify project defenses against threats.
  • Vendor Breach: Address new risk of vendor breach through incident-response and CERT engagement. Implement robust vendor-risk-management practices.
Cybersecurity Resilience image

Slide 8: Plan Harmonization

Integrating Changes into a Cohesive Project Strategy

Image URL: https://www.proofhub.com/articles/wp-content/uploa...
  • WBS Restructuring: The WBS now includes 6 summary tasks, incorporating the Event and Cyber Response initiatives to reflect recent project changes.
  • Gantt Chart Modification: The Gantt chart reflects the extended critical path to Day 250, with branches highlighted to emphasize task dependencies and timelines.
  • Budget Revamp: Budget shows net +£0.45M, with updated Cost Baseline table. Resource allocation has been revised to meet project needs.
  • Risk Management: Risk Plan now includes +7 new risks with mitigation strategies. Clear communication of risk events is crucial.
Plan Harmonization image

Slide 9: The Way Forward

Future Directions and Reflection

Image URL: https://ecdn.teacherspayteachers.com/thumbitem/Sci...
  • Further Research: This thesis is structured to contribute to further research on emerging hybrid methodologies and their applications in different project contexts.
  • Framework Development: A framework for choosing the best hybrid approach for certain projects is developed for better decision-making.
  • Training: Train and develop project managers and team members to strengthen the ability to deliver hybrid methodologies properly to increase success.
  • Long Term Vision: Establish hybrid methodologies as preferred practices, creating a culture of continuous learning within the project management community.
The Way Forward image

Slide 10: Gratitude

Thank you

Image URL: https://images.rawpixel.com/image_800/czNmcy1wcml2...
  • Conclusion of Learning: The experiences learned will be powerful in defining academic and professional pursuits to follow. Reflect on personal contribution.
  • Reflection on Improvement: Looking back at the group project, it has been good to reflect on what you can improve and what you can do better for next time.
  • Collaboration: Life of the collaboration was a helpful experience of teamwork, hybrid methodologies, and personal contribution.
  • A Heartfelt Thank You: Thank you for your attention. We appreciate your time and hope this presentation has been informative and insightful for all of you.